Set Baseline using Csom/PSI #21

@sasankjonna

Description

@sasankjonna

Is there a way to set Baseline dates progrmatically using PSI or CSOM in Project online 365? I understand the below link says we cannot do it for Project 2013, but no such documentation is available for 365.

https://docs.microsoft.com/en-us/office/client-developer/project/what-the-psi-does-and-does-not-do#pj14_WhatPSIDoes_DoesNotDo

We were able to set the baseline using PSI by opening an instance of Winproj.exe and then calling PSI . We can still do it for 365, but just checking if there is a better way to handle it