Is there a way to set Baseline dates progrmatically using PSI or CSOM in Project online 365? I understand the below link says we cannot do it for Project 2013, but no such documentation is available for 365.
We were able to set the baseline using PSI by opening an instance of Winproj.exe and then calling PSI . We can still do it for 365, but just checking if there is a better way to handle it