I made some debugging for finding the cause of unexpected high levelized cost of electricity in some scenarios and I seems that something is not working properly when having a timeseries as the feed-in price for the DSO component.For debugging I made 2 scenarios which should get the same LCOE.
In the reference case the feedinprice is set to 1.5 and the results looks correct on this (negative price in this case)In the 2nd scenario the feedinprice is a timeseries with 1 and 2. As the average is also 1.5 and the feedin is constant 1 it should yield the same result. However it seems there is no revenue calculated at all.
![]()
As in my other scenarios/projects everything is getting optimized as expected, this is not a matter of wrong input or simulation but only an error in the result reading.