Summary

Add comprehensive execution plans for the remaining RDB-004 PolyORB.Any decomposition tasks.

Documents Added

RDB-004-TASK3-EXECUTION-PLAN.md (797 LOC)

Accessor Module Extraction - Task ID: 6a62ba

  • Effort: 10-12 days (80-96 hours)
  • Scope: Extract 2,244 LOC accessor functionality
  • Approach: Two-phase (nested package → separate file)
  • Result: Reduce polyorb-any.adb from 2,600 → 1,600 LOC (38% reduction)

RDB-004-TASK4-EXECUTION-PLAN.md (659 LOC)

CDR Marshalling Extraction - Task ID: fb039e

  • Effort: 7-9 days (56-72 hours)
  • Scope: Extract ~1,000 LOC CDR operations
  • Testing: CORBA interoperability (TAO, omniORB, JacORB)
  • Dependencies: Task 3 completion

RDB-004-TASK5-EXECUTION-PLAN.md (918 LOC)

Utilities Extraction & Finalization - Task ID: 676714

  • Effort: 5-7 days (40-56 hours)
  • Scope: Extract ~550 LOC utility functions
  • Result: Final core reduction to <900 LOC (65% total reduction)
  • Dependencies: Tasks 3 & 4 completion

Timeline

Week Task Duration Deliverable
3-4 (Nov 18 - Dec 1) Task 3: Accessors 10-12 days polyorb-any-accessors module
5 (Dec 2-10) Task 4: CDR 7-9 days polyorb-any-cdr module
6 (Dec 13-20) Task 5: Utilities 5-7 days RDB-004 complete

Total Effort: 22-28 days for Tasks 3-5

Related

Reviewer

@code_architect - Please review execution plans for architectural alignment


🤖 Generated with Claude Code

Add comprehensive execution plans for the remaining RDB-004 PolyORB.Any
decomposition tasks.

Task 3 - Accessor Module Extraction (6a62ba):
- 10-12 days effort (80-96 hours)
- Extract 2,244 LOC accessor functionality
- Two-phase approach: nested package → separate file
- Reduce polyorb-any.adb from 2,600 → 1,600 LOC

Task 4 - CDR Marshalling Extraction (fb039e):
- 7-9 days effort (56-72 hours)
- Extract ~1,000 LOC CDR operations
- CORBA interoperability testing required
- Depends on Task 3 completion

Task 5 - Utilities Extraction & Finalization (676714):
- 5-7 days effort (40-56 hours)
- Extract ~550 LOC utility functions
- Final core reduction to <900 LOC
- Completes RDB-004 decomposition

Timeline: Weeks 3-6 (Nov 18 - Dec 20, 2025)
Total Effort: 22-28 days for Tasks 3-5

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude <noreply@anthropic.com>
@github-actions
Copy link
Copy Markdown

Build Summary - 2aaa9ea

Status

  • C++ Services: success
  • PolyORB Build: failure
  • Test Suite: skipped
  • Docker Images: skipped

Details

  • Commit: 2aaa9ea
  • Branch: 7/merge
  • Triggered by: pull_request
  • Run: 89

Next Steps

  • Review test results in Actions artifacts
  • Check security scan findings in Security tab
  • Deploy to staging if all checks pass

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant