Add comprehensive execution plans for the remaining RDB-004 PolyORB.Any decomposition tasks. Task 3 - Accessor Module Extraction (6a62ba): - 10-12 days effort (80-96 hours) - Extract 2,244 LOC accessor functionality - Two-phase approach: nested package → separate file - Reduce polyorb-any.adb from 2,600 → 1,600 LOC Task 4 - CDR Marshalling Extraction (fb039e): - 7-9 days effort (56-72 hours) - Extract ~1,000 LOC CDR operations - CORBA interoperability testing required - Depends on Task 3 completion Task 5 - Utilities Extraction & Finalization (676714): - 5-7 days effort (40-56 hours) - Extract ~550 LOC utility functions - Final core reduction to <900 LOC - Completes RDB-004 decomposition Timeline: Weeks 3-6 (Nov 18 - Dec 20, 2025) Total Effort: 22-28 days for Tasks 3-5 🤖 Generated with [Claude Code](https://claude.com/claude-code) Co-Authored-By: Claude <noreply@anthropic.com>
Build Summary - 2aaa9eaStatus
Details
Next Steps
|
This file contains hidden or bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Add this suggestion to a batch that can be applied as a single commit.This suggestion is invalid because no changes were made to the code.Suggestions cannot be applied while the pull request is closed.Suggestions cannot be applied while viewing a subset of changes.Only one suggestion per line can be applied in a batch.Add this suggestion to a batch that can be applied as a single commit.Applying suggestions on deleted lines is not supported.You must change the existing code in this line in order to create a valid suggestion.Outdated suggestions cannot be applied.This suggestion has been applied or marked resolved.Suggestions cannot be applied from pending reviews.Suggestions cannot be applied on multi-line comments.Suggestions cannot be applied while the pull request is queued to merge.Suggestion cannot be applied right now. Please check back later.
Summary
Add comprehensive execution plans for the remaining RDB-004 PolyORB.Any decomposition tasks.
Documents Added
RDB-004-TASK3-EXECUTION-PLAN.md (797 LOC)
Accessor Module Extraction - Task ID: 6a62ba
RDB-004-TASK4-EXECUTION-PLAN.md (659 LOC)
CDR Marshalling Extraction - Task ID: fb039e
RDB-004-TASK5-EXECUTION-PLAN.md (918 LOC)
Utilities Extraction & Finalization - Task ID: 676714
Timeline
Total Effort: 22-28 days for Tasks 3-5
Related
Reviewer
@code_architect - Please review execution plans for architectural alignment